Ettix guides · Construction estimating
How to review construction bid addenda before submitting
Before you lock the price, record which addenda you reviewed and where they change the original bid package.
Review one addendum free Download the Excel checklist
1. Check the official list of issued addenda
Record the solicitation ID and every addendum number from the issuing portal. If your folder is missing a listed file, obtain it before reviewing the package.
2. Verify the deadline and submission instructions
Record the previous deadline and the updated date, time and time zone. Check whether the submission location or the acknowledgement instructions changed.
3. Separate quantity and scope changes
Identify the affected item or specification, its source page and the change to price or schedule. For an illustrative lighting item revised from 48 to 64 fixtures, review the additional 16 fixtures and any related work before pricing.
4. Check the replacement drawings
Record each sheet number mentioned in the addendum. Open the actual drawings to verify revisions. A text check can flag a sheet reference, while drawings and scanned pages still require visual review.
5. Keep the evidence with the bid
Assign each item for review and note the resulting estimate update. In Pawtucket's public RFQ 24-034, Addendum 1 revises the scope in section 4.0 to include additional projects and directs bidders to acknowledge the addendum. Check that instruction in the issuing document for your own solicitation.
Open BidAddenda and try the illustrative example. Files are processed in your browser.
Public examples Pawtucket RFQ 24-034, Addendum 1 · MnDOT addendum process.